Question: Bradley is working on establishing the baselines for the project. He is working on the combination of project scope statement, WBS and Work package and
Bradley is working on establishing the baselines for the project. He is working on the combination of project scope statement, WBS and Work package and planning package. The baseline that Bradley is working on is called?
A. Project baseline.
B. Scope baseline.
C. Requirement baseline.
D. Product baseline.