Question: Decomposition is a technique used for both WBS development and activity definition. However, in Define Activities, decomposition- A. The final output is described in terms

Decomposition is a technique used for both WBS development and activity definition. However, in Define Activities, decomposition-

A. The final output is described in terms of work packages in the WBS.

B. The final output is described as deliverables or tangible items.

C. * The final output is described as activities.

D. Is used the same way in scope definition and activity definition.