Question: For a project with SV = $200 and CV = $200, what conclusion can be made on the project status? (a) You are ahead of
For a project with SV = −$200 and CV = −$200, what conclusion can be made on the project status?
(a) You are ahead of schedule and below budget
(b) You are behind schedule and over budget
(c) You are on schedule and on budget
(d) None of the above