Question: Gantt chart A. A sequence of tasks that must be accomplished within a certain time frame to achieve a desire result. B. A factor, such

Gantt chart A. A sequence of tasks that must be accomplished within a certain time frame to achieve a desire result.

B. A factor, such as budget or time, that limits a project manager’s options.

C. * A horizontal bar chart that graphically displays project tasks and durations.

D. An interactive Web-based seminar or training session.