Question: If earned value = 1,000, planned value = 1,400 and actual cost = 1,200, the cost performance index is A. 1.2 B. 0.9 C. 0.714

If earned value = 1,000, planned value = 1,400 and actual cost =

1,200, the cost performance index is A. 1.2 B. 0.9 C. 0.714 D. * 0.833