Question: Joe is a project manager on a large software project. Very late in his project, the customer asked for a huge change and wouldnt give
Joe is a project manager on a large software project. Very late in his project, the customer asked for a huge change and wouldn’t give him any more time to complete the project. At a weekly status meeting, the client demanded that the project be finished on time. Joe told the client that he wasn’t going to do any more status meetings until the client was ready to be reasonable about the situation. Which conflict resolution technique was he using?
A. Forcing B. Compromise C. * Withdrawal D. Confronting