Question: Project cost control includes all of the following EXCEPT: A. Informing appropriate stakeholders of all approved changes and associated costs. B. Monitoring cost performance to
Project cost control includes all of the following EXCEPT:
A. Informing appropriate stakeholders of all approved changes and associated costs.
B. Monitoring cost performance to isolate and understand variances from the approved cost baseline.
C. Influencing the factors that create changes to the authorized cost baseline.
D. * Allocating the overall estimates to individual work packages to establish a cost baseline.