Question: The basis for continuous quality improvement is the: A. * Plan-do-check-act (PDCA) cycle as defined by Shewhart and modified by Deming. B. Process decision program

The basis for continuous quality improvement is the:

A. * Plan-do-check-act (PDCA) cycle as defined by Shewhart and modified by Deming.

B. Process decision program chart (PDPC).

C. Ready-aim-fire (RAF) cycle linked by results.

D. Conceptualize-design-execute-finish (CDEF) cycle.