Question: The project manager recognizes his team may fail to meet a deadline, so he assigns the team to do two activities in parallel. This is

The project manager recognizes his team may fail to meet a deadline, so he assigns the team to do two activities in parallel. This is an example of schedule:

A. crashing.

B. * fast tracking.

C. leading.

D. shortening.