Question: The project manager recognizes his team may fail to meet a deadline, so he assigns the team to do two activities in parallel. This is
The project manager recognizes his team may fail to meet a deadline, so he assigns the team to do two activities in parallel. This is an example of schedule:
A. crashing.
B. * fast tracking.
C. leading.
D. shortening.