Question: The project manager would like to show the rate at which the project is progressing compared to what was planned. What indicator should she reference?
The project manager would like to show the rate at which the project is progressing compared to what was planned. What indicator should she reference?
A. Gantt chart B. schedule variance C. variance report D. * schedule performance index
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
