Question: Tucker is the construction project manager for a new school building. He measures the projects performance and progress by looking at the planned value, earned
Tucker is the construction project manager for a new school building. He measures the project’s performance and progress by looking at the planned value, earned value, and actual cost. Which method is Tucker using to determine the project performance?
A. forecasting B. performance review(s)
C. cost management plan D. * earned value management