Question: what is bottom up estimating? A. * When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is

what is bottom up estimating?

A. * When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail.

The resource needs are estimated.

B. Has the capability to help plan, organize, and manage resource pools and develop resource elements C. The accuracy of activity duration estimates can be improved by considering estimation uncertainty and risk.