Question: What is the correct sequence of the six process in the project time management? i. Plan schedule management ii. Sequence activities iii. Estimate activity duration

What is the correct sequence of the six process in the project time management? i. Plan schedule management ii. Sequence activities iii.

Estimate activity duration iv. Develop schedule v. Estimate activity resources vi. Defined activities A. i,iv,vi,ii,v,iii B. * i,vi,ii,v,iii,iv C. vi,I,ii,iii,v,iv