Question: Which process requires the project manager to analyze the network diagram and sequencing to see whether any activities can be done in parallel on the
Which process requires the project manager to analyze the network diagram and sequencing to see whether any activities can be done in parallel on the critical path?
A. crashing B. * fast tracking C. leading D. shortening