Question: Which statement of WBS below is incorrect? A. WBS is useful for complex projects B. WBS defines the work required to achieve an objective C.

Which statement of WBS below is incorrect?

A. WBS is useful for complex projects B. WBS defines the work required to achieve an objective C. * WBS provides timing of activities D. WBS is a tool for planning & scheduling a project