Question: You have recently been assigned as a project manager to manage a project that was terminated six months ago because of funding-related issues, but which
You have recently been assigned as a project manager to manage a project that was terminated six months ago because of funding-related issues, but which has since been re-initiated. You want to find out the exact reasons for the termination of the project. You also want to know which deliverable were produced from the terminated project. Which of the following documentation should you review to obtain this information?
A. * Project or Phase Closure Document B. Project Document C. Supporting document D. Final product/services