Question: You have been given schedule estimates for a small building construction with the following activities: Time to complete Predecessor A . Prepare foundation 5 days

You have been given schedule estimates for a small building construction with the following activities:
Time to complete Predecessor
A. Prepare foundation 5 days
B. Assemble the building 4 days A
C. Finish Interior 4 days B
D. Building inspection 11 days B
E. Do the landscaping 5 days C
F. Pave the driveway 2 days C
G. Paint the structure 5 days E, F
H. Arrange the sale 3 days D, G
a. Create a GANTT Chart using Excel or Word. Make sure to label axis, and provide a title.
b. Create an AON network diagram showing ES, LS, EF, LS. Show a legend.
c. What is the critical path for this project and how long is it?
d. Identify all the paths through the network diagram and their durations.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!