Question: You have been given schedule estimates for a small building construction with the following activities: Time to complete Predecessor A . Prepare foundation 5 days
You have been given schedule estimates for a small building construction with the following activities:
Time to complete Predecessor
A Prepare foundation days
B Assemble the building days A
C Finish Interior days B
D Building inspection days B
E Do the landscaping days C
F Pave the driveway days C
G Paint the structure days E F
H Arrange the sale days D G
a Create a GANTT Chart using Excel or Word. Make sure to label axis, and provide a title.
b Create an AON network diagram showing ES LS EF LS Show a legend.
c What is the critical path for this project and how long is it
d Identify all the paths through the network diagram and their durations.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock