Question: 0/100 - Task B is allocated 1000 hours to begin work on day 1. It began one month late due to delays in other parts
0/100 - Task B is allocated 1000 hours to begin work on day 1. It began one month late due to delays in other parts of the project and as a result it finished one month later than originally anticipated. At the end of the task, it used 1000 hours of labor. At the end of Month 1, what are the SV and CV?