Question: 01.Construct a network using the information in the table (must draw the network in answer) 02.and identify the critical path (write the activity letter) 03.

01.Construct a network using the information in

01.Construct a network using the information in the table (must draw the network in answer) 02.and identify the critical path (write the activity letter) 03. compute early and late start times like example

01.Construct a network using the information in

Activity IB IC D E IF IG H Time 14 16 19 11 16 14 18 17 Predecessor IA A B B, C ID E, F G Task Early Start Early Finish Late Start Late Finish A 10 4 10 14 B 14 10 C D E F G H 13