Question: C . The table below defines the activities within a small project. table [ [ Activity , table [ [ Completion time ]

C. The table below defines the activities within a small project.
\table[[Activity,\table[[Completion time],[(weeks)]],\table[[Immediate],[predecessor activities]]],[A,2,-],[B,3,-],[C,4,A],[D,3,A, B],[E,8,C, D],[F,3,C],[G,2,E],[H,3,F, G]]
I. Draw the network diagram using AOA.
II. Calculate the minimum overall project completion time and identify which activities are critical.
III. What is the slack (float) time associated with each of the activities.Draw the network and determine the critical path of the project whose activities are listed i
table below using AOA
 C. The table below defines the activities within a small project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!