Question: 6. Processing times including setup times and due dates for six jobs waiting to be processed at the work center are given in the following

6. Processing times including setup times and due

6. Processing times including setup times and due dates for six jobs waiting to be processed at the work center are given in the following table. Using the FCFS Determine: (a) The sequence of jobs, [3] (b) The average flow time, [3] (c) Average tardiness [3] (d) Average number of jobs at the work center. [4] Job Processing time(days) Due Date() A 2 7 B ca 16 4 4 D 10 17 E 5 15 F 12 18 Note: Assume jobs arrived in the order shown