Question: 1 0 0 . Non - critical activities are distinguished by the presence of a . positive slack. b . idle resources. c . wasted

100. Non-critical activities are distinguished by the presence of
a. positive slack.
b. idle resources.
c. wasted time.
d. zero slack.