Question: 1 0 . 1 1 Given the following information, answer the questions about this project: table [ [ Activity , Expected Duration,Predecessors ] ,
Given the following information, answer the questions about this project:
tableActivityExpected Duration,PredecessorsA days,B daysCA days,AD days,BE days,BF days,CG days,D FH days,E G day,H
a Draw the network as a Gantt chart
b What is the critical path? Which activities have slack time?
c What would happen If activities B and D each took extra days to complete instead of the expected duration? How would the critical path change?