Question: 1 0 . 7 table [ [ Activity , COST,April,May,June,July,August,Sept ] , [ A , $ 5 0 , , , , , ,
tableActivityCOST,April,May,June,July,August,SeptA$B$C$$D$E$F$$G$H$J$K$
After months on the job July the contractor concluded that of Activity F Activities A B and D are completed was completed, of Activity C was completed, and of Activity E was completed. The project has cost the contractor a total of $ For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under the budget and if it is ahead or behind schedule.