Question: Earned value analysis 1. After 3 months on the job (July 1), the contractor concluded that the following work was complete: a. 20% of activity

Earned value analysis
Earned value analysis 1. After 3 months on the
1. After 3 months on the job (July 1), the contractor concluded that the following work was complete: a. 20% of activity F b. activity A, C. activity B d. activity D e. 80% of activity C The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the project status. State if the project is over or under budget and if it is ahead or behind schedule. Activity Cost April May June July August Sept A B D $50 $120 $80 $200 $120 $300 $60 E F G H $70 J $50 K $60