Question: Earned value analysis 1. After 3 months on the job (July 1), the contractor concluded that the following work was complete: a. 20% of activity
Earned value analysis
1. After 3 months on the job (July 1), the contractor concluded that the following work was complete: a. 20% of activity F b. activity A, C. activity B d. activity D e. 80% of activity C The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the project status. State if the project is over or under budget and if it is ahead or behind schedule. Activity Cost April May June July August Sept A B D $50 $120 $80 $200 $120 $300 $60 E F G H $70 J $50 K $60
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
