Question: 1. (10 points) For the Given project, determine the following Activity Time (weeks) Immediate Predecessor A B D E F G A A B DE

1. (10 points) For the Given project, determine

1. (10 points) For the Given project, determine the following Activity Time (weeks) Immediate Predecessor A B D E F G A A B DE F | | 4 5 4 7 a. Draw the diagram and determine the ES, EF, LS, and LF. (Clearly label) b. What is the slack and the critical path