Question: 1. (10 points) For the Given project, determine the following Activity Time (weeks) Immediate Predecessor A B A A B 2 5 6 4 5

1. (10 points) For the Given project, determine the following Activity Time (weeks) Immediate Predecessor A B A A B 2 5 6 4 5 D E D E F G DE F 4 7 a. Draw the diagram and determine the ES, EF, LS, and LF. (Clearly label b. What is the slack and the critical path