Question: 1 3 . 7 ?Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through

1 3 . 7 ?Using the data in the table below, complete the table by calculating the cumulative
planned and cumulative actual monthly budgets through the end of June. Complete the
earned value column on the right. Assume the project is planned for a 1 2 - month duration
and $ 2 5 0 , 0 0 0 ?budget.
Activity Jan Feb Mar Apr May Jun Plan % ?C Value
Staffing 8 7 1 5 1 0 0 ?
Blueprinting 4 6 1 0 1 0 0 ?
Prototype
?Development 2 8 1 0 7 0 ?
Full Design 3 8 1 0 2 1 6 7 ?
Construction 2 3 0 3 2 2 5 ?
Transfer 1 0 1 0 0 ?
Monthly Plan
Cumulative
Monthly Actual 1 0 1 5 6 1 4 9 4 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!