Question: 1 . 3 . A software development project at day 7 0 exhibits an actual cost of $ 7 8 , 0 0 0 and

1.3. A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000. The software manager estimates a value completed of
$81,000.WhatarethecostandschedulevariancesandCSI? Estimatethetimevariance.