Question: 3. A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000 The software manager estimates a
3. A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled cost of $84,000 The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance