Question: a . A software development project at day 7 0 exhibits an actual cost of $ 7 8 , 0 0 0 and a scheduled

a. A software development project at day 70 exhibits an actual cost of $78,000 and a scheduled
cost of $84,000. The software manager estimates a value completed of $81,000. What are the
cost and schedule variances and CSI? Estimate the time variance.
b. A consulting project has an actual cost in month 10 of $23,000, a scheduled cost of $17,000,
and a value completed of $20,000. Find the schedule and cost variances and the three indexes