Question: 1 4 . Calculate the ES , EF , LS , and LF times and the slack for each activity in the figure below, and

14. Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below, and identify the critical path for the project. Can the project be completed in 30 weeks? Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 15 weeks, and Design Database actually finished at 19 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?
Activity ED ES EF LS LF TS
1. Prob. Def.
2. Sys. Analysis
3. Design I/O
4. Design DB
5. Develop Input
6. Develop Output
7. Develop DB
8. Test System
9. Implement
Critical path:
Can the project be completed in 30 weeks?
Activity ED ES EF LS LF TS AF
1. Prob. Def.
2. Sys. Analysis
3. Design I/O
4. Design DB
5. Dev. Input
6. Dev. Output
7. Dev. DB
8. Test System
9. Implement
Which activities would you focus on in order to get the project back on schedule?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!