Question: 1 a )LLED Computers assembles Custom personal computers for the gaming market. It's most popular model XT-80 Is currently selling at a rate of 300

1 a )LLED Computers assembles Custom personal computers for the gaming market. It's most popular model XT-80 Is currently selling at a rate of 300 per week. THE XT-80 Can be configured with a gaming hardware kit, which is comprised of a carrying case, a gaming headset and a racing wheel. One in every four customers is ordering the gaming hardware kit. Currently LLED Assembles the gaming hardware kits in batches of 100. LLED Currently has an open order for 75 racing wheels to be delivered in Week 3. Develop a ten-week MRP records for the XT80 the gaming hardware kit and the racing wheel. Using the following information.

1 a )LLED Computers assembles Custom personal

1b)The LLED manager of the assembly plant has decided that rather than assembling the gaming hardware kits ahead of time, they would incorporate the assembly into the same work cell Phantom assembly that assembles the finished. Xt-80 Given that change, recalculate the MRP records for the. Xt-80 Gaming hardware kits and the racing wheel.

1 a )LLED Computers assembles Custom personal

LLED Computers assembles Custom personal computers for the gaming market. It's most popular model XT-80 is currently selling at a rate of 300 per week. THE XT-80 Can be configured with a gaming hardware kit, which is comprised of a carrying case, a gaming headset and a racing wheel. One in every four customers is ordering the gaming hardware kit. Currently LLED Assembles the gaming hardware kits in batches of 100. LLEDD Currently has an open order for 75 racing wheels to be delivered in Week 3. Develop a ten-week MRP records for the XT80 the gaming hardware kit and the racing wheel. Using the following information. part XT-80 gaming kit racing wheel Lot size Safety Stock Lead time Scrap Rate Current Inventory LAL 0 1 0 320 100 25 1 ol 110 75 50 3 5 230 1 21 3 4 S 6 7 8 9 10 XT-80 WK Gross Requirements Scheduled Receipts PAB Planned release planned rec 2 3 4 5 6 7 8 9 10 Hardware set WK Gross Requirements Scheduled Receipts PAB Planned release planned rec 1 2 3 4 5 6 7 8 91 10 Racing Car WK Gross Requirements Scheduled Receipts PAB Planned release planned rec The LLED manager of the assembly plant has decided that rather than assembling the gaming hardware kits ahead of time, they would incorporate the assembly into the same work cell Phantom assembly that assembles the finished. Xt-80 Given that change, recalculate the MRP records for the. Xt-80 Gaming hardware kits and the racing wheel. part XT-80 gaming kit racing wheel Lot size Safety Lead time Scrap Rate Current Inventory L4L 0 1 0 320 100 25 1 0 110 75 50 3 5 230 1 2 3 4 5 6 7 8 9 10 XT-80 WK Gross Requirements Scheduled Receipts PAB Planned release planned rec 1 2 3 4 5 6 7 8 9 10 Hardware set WK Gross Requirements Scheduled Receipts PAB Planned release planned rec 1 2 3 4 5 6 7 8 9 10 Racing Car WK Gross Requirements Scheduled Receipts PAB Planned release planned rec

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!