Question: 1. A network diagram is drawn using the Activity on Arrow (AOA) format. Find ES, LS, EF, LF, and slack numbers all activities. Immediate Predecessor

1. A network diagram is drawn using the Activity

1. A network diagram is drawn using the Activity on Arrow (AOA) format. Find ES, LS, EF, LF, and slack numbers all activities. Immediate Predecessor Activity a. organize team 1 b. organize team 2 c. design personnel jobs d. set machinery in place e. connect utilities f. modify conveyor system g. train personnel h. finishing touches , run test lot a b sd e Duration (days) 5 3 2 3 7 4 3 5 2 4 OD a f f h 5 8 b b d g i 7