Question: 1) A project status report shows that the earned value (EV) IS 24.5, the schedule performance index (SPI) is 0.92, and the cost performance (CPI)
1) A project status report shows that the earned value (EV) IS 24.5, the schedule performance index (SPI) is 0.92, and the cost performance (CPI) is 1.06. in what area should the project manager implement corrective actions? A. Stakeholder engagement B. Project schedule C. Project cost D. Resource management
2) During a weekly status meeting, a key stakeholder complains that quality standards for some project deliverables are unmet. What should the project manager do? A. Document the issue in the lessons learned B. Update the project management plan C. Record the issue in the issue log D. Create a change request