Question: 1. Activity Activity Time (5 day weeks) Immediate Predecessors A 4 none B 3 A C 5 A D 2 A E 5 B, C
1.
| Activity | Activity Time (5 day weeks) | Immediate Predecessors |
| A | 4 | none |
| B | 3 | A |
| C | 5 | A |
| D | 2 | A |
| E | 5 | B, C |
| F | 6 | C, D |
| G | 4 | E, F |
| H | 3 | G |
What is ES and EF for G?
| A. | 14, 18 | |
| B. | 15,19 | |
| C. | 16, 20 | |
| D. | 17, 21 |
2.
As a project manager what example did I give for building consensus and agreements?
| A. | I worked very closely with all suppliers, current and prospective | |
| B. | During equipment installation I should have spent time on the shop floor with operators | |
| C. | I worked closely only with my boss | |
| D. | I would not allow suppliers on the shop floor | |
| E. | I accepted gifts that I shouldn't have |
3.
If scope creep is allowed to occur during a project:
| A. | Team members feel compelled to fix problems that they encounter during the project | |
| B. | Project managers expand their responsibility to other companies | |
| C. | Personnel become obsessed with finishing the project ahead of schedule | |
| D. | Project team members have two bosses | |
| E. | Matrix mgt is out of control |
4.
What seems to be the overarching symptom which causes projects to fail?
| A. | Lack of technical expertise | |
| B. | Lack of funds | |
| C. | Poor planning | |
| D. | Resources not committed | |
| E. | Lack of upper mgt. commitment |
5.
One thing that could cause problems for a project manager attempting to use the "project buffer" approach for estimating:
| A. | Large number of activities | |
| B. | Harsh reprimands in the past to team members finishing activities late | |
| C. | Technology changes | |
| D. | Team members accepting gifts | |
| E. | Random variation |