Question: Activity Activity Time (5 day weeks) Immediate Predecessors (A 4 none )(B 3 A) (C 5 A)( D 2 A) (E 5 B, C) (F
Activity Activity Time (5 day weeks) Immediate Predecessors (A 4 none )(B 3 A) (C 5 A)( D 2 A) (E 5 B, C) (F 6 C, D) (G 4 E, F) (H 3 G)
What is the activity slack for C?
A. 1 B. 3 C. 2 D. 4 E. 0