Question: Activity Activity Time (5 day weeks) Immediate Predecessors A 4 none B 3 A C 5 A D 2 A E 5 B, C F

Activity

Activity Time

(5 day weeks)

Immediate Predecessors

A

4

none

B

3

A

C

5

A

D

2

A

E

5

B, C

F

6

C, D

G

4

E, F

H

3

G

What is ES and EF for G?

A.

14, 18

B.

15,19

C.

16, 20

D.

17, 21