Question: Activity Activity Time (5 day weeks) Immediate Predecessors A 4 none B 3 A C 5 A D 2 A E 5 B, C F
Activity Activity Time (5 day weeks) Immediate Predecessors A 4 none B 3 A C 5 A D 2 A E 5 B, C F 6 C, D G 4 E, F H 3 G What is the critical path?
A. ABEGH B. ACEGH C. ACFGH D. ADFGH