Question: 1. Compute earned value for every package. 2. What is the CV Cost Variance and SV Schedule Variance at the end of week 7 3.What

1. Compute earned value for every package. 2.

1. Compute earned value for every package.

2. What is the CV Cost Variance and SV Schedule Variance at the end of week 7

3.What is the Cost Performance Index and Schedule Performance Index at the end of week 7?

Use the following table of cumulative percentages of work completed to determine the cumulative earned value (EV) of the project at the end of week 7. BAC 50 Week 1 25% 2 80% 100% 4 100% 5 100% 6 100% 7 100% Task 1 Task 2 90 10% 20% 22% 45% 75% 80% Task 3 60 10% 25% 35% 60% Total Use the following table of cumulative percentages of work completed to determine the cumulative earned value (EV) of the project at the end of week 7. BAC 50 Week 1 25% 2 80% 100% 4 100% 5 100% 6 100% 7 100% Task 1 Task 2 90 10% 20% 22% 45% 75% 80% Task 3 60 10% 25% 35% 60% Total

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!