Question: 1. Compute earned value for every package. 2. What is the CV Cost Variance and SV Schedule Variance at the end of week 7 3.What

1. Compute earned value for every package.
2. What is the CV Cost Variance and SV Schedule Variance at the end of week 7
3.What is the Cost Performance Index and Schedule Performance Index at the end of week 7?
Use the following table of cumulative percentages of work completed to determine the cumulative earned value (EV) of the project at the end of week 7. BAC 50 Week 1 25% 2 80% 100% 4 100% 5 100% 6 100% 7 100% Task 1 Task 2 90 10% 20% 22% 45% 75% 80% Task 3 60 10% 25% 35% 60% Total Use the following table of cumulative percentages of work completed to determine the cumulative earned value (EV) of the project at the end of week 7. BAC 50 Week 1 25% 2 80% 100% 4 100% 5 100% 6 100% 7 100% Task 1 Task 2 90 10% 20% 22% 45% 75% 80% Task 3 60 10% 25% 35% 60% Total