Question: 1 . Consider a manufacturing system under MRP control. The master production schedule over the next five weeks for a given end item is as
Consider a manufacturing system under MRP control. The master production schedule over the next five weeks for a given end item is as follows:
Week
Demand
There are currently items in inventory and more are scheduled to be arriving at the beginning of week ie scheduled receipts in week The assemble lead time is weeks for this end item. The end item consists of two purchased parts.
a
What is the independent demand & dependent demand entities in this problem? Explain why?
b
Compute planned order releases for the end item.
c
Let ordering cost be $ and holding cost per week be $ For the planned order releases of the end item, determine lot sizing using.
a
Lotforlot
b
Silver meal
c
Part balancing
d
The two purchased parts Part A and Part B have a lead time of week. Currently, Part A and Part B has units in inventory. Compute planned order releases for Part A Note: only for Part A Is the MPS still feasible
e
Say, for the end item, the scheduled receipts are delayed by a week. The units are scheduled to be arriving at the beginning of week instead of beginning of week Can we meet the MPS quantities for the end item
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
