Question: 1 . Consider a manufacturing system under MRP control. The master production schedule over the next five weeks for a given end item is as

1. Consider a manufacturing system under MRP control. The master production schedule over the next five weeks for a given end item is as follows:
Week
0
1
2
3
4
5
Demand
41
71
14
92
112
There are currently 100 items in inventory and 20 more are scheduled to be arriving at the beginning of week 2(i.e.) scheduled receipts in week 2. The assemble lead time is 2 weeks for this end item. The end item consists of two purchased parts.
a)
What is the independent demand & dependent demand entities in this problem? Explain why?
b)
Compute planned order releases for the end item.
c)
Let ordering cost be $350 and holding cost per week be $2.50. For the planned order releases of the end item, determine lot sizing using.
a.
Lot-for-lot
b.
Silver meal
c.
Part balancing
d)
The two purchased parts (Part A and Part B) have a lead time of 1 week. Currently, Part A and Part B has 50 units in inventory. Compute planned order releases for Part A (Note: only for Part A). Is the MPS still feasible ?
e)
Say, for the end item, the scheduled receipts are delayed by a week. The 20 units are scheduled to be arriving at the beginning of week 3(instead of beginning of week 2). Can we meet the MPS quantities for the end item ?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!