Question: 1. Consider a project that has been modeled as in Table 1. Table 1: Activities and Predecessors Activity Immediate Predecessors Duration Activity, predececor, duration A7
1. Consider a project that has been modeled as in Table 1.
Table 1: Activities and Predecessors Activity Immediate Predecessors Duration
Activity, predececor, duration
A7
BA6
CA3
D B,C 12
E B,C 14
F D,E 5
a. Suppose the standard deviations of the activity durations are A = 2, B =1,C =0,D =2,E =3,andF =0. Then please estimate the standard deviation of the overall projects standard deviation P .