Question: Please show all your work neatly. 1. Consider a project that has been modeled as in Table 1. Table 1: Activities and Predecessors Activity Immediate

Please show all your work neatly. Please show all your work neatly. 1. Consider a
1. Consider a project that has been modeled as in Table 1. Table 1: Activities and Predecessors Activity Immediate Predecessors Duration A 7 B A 6 A 3 D 12 E B,C 14 F DE 5 B,C Draw the PERT/CPM network for this project and determine the project's ex- pected completion time and its critical path