Question: 1. Consider the following data for a project: Activity Time Immediate Activity (days) Predecessor(s) A 3 B 4 A 5 A D 2 B E
1. Consider the following data for a project: Activity Time Immediate Activity (days) Predecessor(s) A 3 B 4 A 5 A D 2 B E 1 B F 9 B, C G 3 D, E H 5 F 1 4 F J 7 G, H, I a. Draw the AON network diagram (with ES, EF, LS, LF, and Slack time) b. Identify all paths in this project c. Determine the project's critical path and duration