Question: 1. Consider the following Project activities. Activity Immed. Completion Predec. Time (Hr) A 6 B 4.5 3 D A 5 E A 1 F B,C

1. Consider the following Project activities.
1. Consider the following Project activities. Activity Immed. Completion Predec. Time (Hr) A 6 B 4.5 3 D A 5 E A 1 F B,C 4 G B,C 1.5 H EF 6 1 E.F 5 J DH 2.75 K GI 5 Name the critical path of this project and the completion time of the project. (Network diagram is not required to be submitted.)