Question: consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none 1 B none 3 C A 6 D A 3 E B,
consider the following project management problem: Task Immediate Predecessor(s) Duration (Days) A none 1 B none 3 C A 6 D A 3 E B, D 4 F C, E 1 a. What is the expected completion time of this project? b. What is critical path through this project?
b.. What is critical path through this project?
c. Draw diagram please