Question: 1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following set of tasks. Use the task number, duration, and

1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following set of tasks. Use the task number, duration, and dependencies of each task given and construct a schedule so that the project is completed in the least number of days possible. Include a management reserve of approximately 10%.

Task

Subject

Duration

Dependencies

Slack (3 pts)

1.0

Project Kickoff

2

none

2.1

Install & Test Database Software

2

1.0

2.2

Configure & Test Database Web API

2

2.1

2.3

Develop & Test Modeling Software

8

1.0

2.4

Develop Reporting Software

5

1.0

3.1

Integration Test: DB API & Model

2

2.2 and 2.3

3.2

Test Reporting Software

2

2.2 and 2.4

4.0

Final Integration/Acceptance Testing

5

3.1 and 3.2

5.0

Closeout

2

4.0

2. Draw the Network Diagram and calculate the early and late schedules

3. What tasks, in order, are on the critical path?

4. Draw the Schedule as a Gantt Chart?

5. What does the graphical representation of the WBS look like for the project?

Note: only the terminal graph nodes are shown in the tasks above; construct logical section titles where needed!

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!