Question: 1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following set of tasks. Use the task number, duration, and
1. Create a network diagram and project schedule (illustrated in a Gantt chart) from the following set of tasks. Use the task number, duration, and dependencies of each task given and construct a schedule so that the project is completed in the least number of days possible. Include a management reserve of approximately 10%.
| Task | Subject | Duration | Dependencies | Slack (3 pts) |
| 1.0 | Project Kickoff | 2 | none | |
| 2.1 | Install & Test Database Software | 2 | 1.0 | |
| 2.2 | Configure & Test Database Web API | 2 | 2.1 | |
| 2.3 | Develop & Test Modeling Software | 8 | 1.0 | |
| 2.4 | Develop Reporting Software | 5 | 1.0 | |
| 3.1 | Integration Test: DB API & Model | 2 | 2.2 and 2.3 | |
| 3.2 | Test Reporting Software | 2 | 2.2 and 2.4 | |
| 4.0 | Final Integration/Acceptance Testing | 5 | 3.1 and 3.2 | |
| 5.0 | Closeout | 2 | 4.0 |
2. Draw the Network Diagram and calculate the early and late schedules
3. What tasks, in order, are on the critical path?
4. Draw the Schedule as a Gantt Chart?
5. What does the graphical representation of the WBS look like for the project?
Note: only the terminal graph nodes are shown in the tasks above; construct logical section titles where needed!