Question: 1. Design capacity is the maximum possible output given a product mix, scheduling difficulties, quality factors, and so on. True or False 2. If a

1. Design capacity is the maximum possible output given a product mix, scheduling difficulties, quality factors, and so on.

True or False

2. If a workers efficiency on a job is 120%, we can conclude that the nominal capacity for the job is higher than the design capacity

True or False

3. Increasing productivity and quality simultaneously will result in increased capacity.

True or False

4. The difference between capacity bills and resource profiles is that resource profiles consider lead time offsets in their calculations.

True or False

5. I/O control is used to control production capacity needed for orders that have been released to the shop floor.

True or False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!