Question: 1. Differences between the DMAIC and DMADV Processes include: Select one: a. the goals the team sets b. the outcome of the completed project 2.

1. Differences between the DMAIC and DMADV Processes include:

Select one:

a. the goals the team sets

b. the outcome of the completed project

2. ________ is a closely managed process of creating a culture accepting of change within an organization.

Select one:

a. DMAIC

b. DMADV

c. change management

d. culture of change

c. the final two phases

d. the improvements; i.e. delivering better quality, efficiency, increasing profits and efficiency

e. Some of the above

f. All of the above

3. In this phase, teams use data to validate their assumptions about a process or problem.

Select one:

a. Define

b. Measure

4. In this phase, loose ends are tied and the project is transitioned to a daily work environment.

Select one:

a. Define

b. Measure

c. Analyze

d. Improve/Design

e. Control/Verify

c. Analyze

d. Improve/Design

e. Control/Verify

5. In this phase, teams develop hypotheses about casual relationships between inputs and outputs, narrow causation down to the vital few, and use statistical analysis and data to validate the hypotheses and assumptions they've made so far.

Select one:

a. Define

b. Measure

c. Analyze

d. Improve/Design

e. Control/Verify

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!