Question: #1) Following information is available about a project. Activity Activity Time (weeks) Immediate Predecessor(s) A 4 - B 4 - C 5 - D 4
#1) Following information is available about a project.
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 4 | - |
| B | 4 | - |
| C | 5 | - |
| D | 4 | - |
| E | 6 | A |
| F | 2 | B,C,D |
| G | 4 | E.F |
| H | 6 | F |
- Compute slack for each activity and determine completion time for the project?
| Activity | Slack |
| A |
|
| B |
|
| C |
|
| D |
|
| E |
|
| F |
|
| G |
|
| H |
|
The project completion time is: __________________ weeks?